Contract Terminated due to fundamental breach
| Name | CDB No. | Start of Exclusion | End of Exclusion |
|---|---|---|---|
| Nill |
Contractor who has failed to complete the contract works within the maximum Liquidated Damage Period (LDP) but has ultimately completed the work.
| Name | CDB No. | Start of Exclusion | End of Exclusion |
|---|---|---|---|
| Nill | Nill | Nill | Nill |
Contractor who failed to sign the contract being lowest evaluated bidder and issuance of Letter of Intent, Letter of Acceptance. (Bid Security not forfeited).
| Name | BCTA/CDB No. | Start of Exclusion | End of Exclusion |
|---|---|---|---|
| Nill | Nill | Nill | Nill |
List of Contractors for Exclusion
| Name | CDB No. | Name of CEO | CID no. |
|---|---|---|---|
| M/s Gaseb & Construction |
1657 | Thinley Tenzin | 10711001472 |
List of Contractors having pending cases( Court/arbitration) with the Ministry
| Name of Contractor | CDB No. | Name of CEO/Proprietor | CID no. | Remarks |
|---|---|---|---|---|
| Welfare Construction Pvt Ltd |
2294 | Ugyen Norbu | 11405000030 | Enforcement |
| Singye Construction Pvt Ltd |
2148 | Ugyen Tshechap Dorji | 11410005860 | High Court/no further info |
| Phuntsho Rabten & Construction Pvt Ltd |
1836 | Ugyen Dorji | 106080014612 | Enforcement |
| UP Construction Pvt Ltd |
3329 | Dorji Tshewang | 10601001051 | Supreme Court |
| Ringdrel Construction Pvt Ltd |
4637 | Yeshi Dorji | 10703001871 | Enforcement |
| Druk Lhayuel Construction Pvt Ltd |
1664 | Pelden Dorji | 10805000429 | Enforcement/Supreme Court |
| Raven Builder Pvt Ltd |
2356 | Thinley Wangchuk | 11505003430 | Enforcement |
| Gadhen Construction |
3972 | Choden | 11315001206 | Enforcement |
| Lhawang Gyajin Construction Pvt Ltd |
5007 | Yeshi Dorji | 11601001223 | Enforcement |
| Gaseb & Construction Pvt Ltd |
1657 | Thinley Tenzin | 11907000209 | Enforcement |
| CD Construction Pvt Ltd |
2452 | Chenga | 11505005191 | Enforcement |
| Samden Nidup Construction |
3039 | Wangdi | 11315001205 | Enforcement |
| Yarkay Group of Pvt Ltd & Zeocrete Pavement Construction Technology Pvt Ltd |
2631 | Phub Zam | 10211002793 | ACC |
| Joenshing Construction |
5728 | Yeshey | 10803000156 | High Court |
| Diana Construction |
7876 | Chimi Gyeltshen | 10602000866 | High Court |
| Tundi & Tacho Construction(JV) |
2001 | Tashi Tshering | 10808000738 | High Court |
| Norzang Construction Pvt Ltd |
7906 | Samten Tshering | 119110000954 | Arbitral Tribunal |
| Sangay L Construction |
7909 | Sangay Lethro | 12007002109 | Arbitral Tribunal |
| Kenzum Construction |
8859 | Mendrel Zangmo | 12003001817 | Arbitral Tribunal |